Light rail construction requires lane restrictions at SE Holgate Blvd and 17th from Sept. 12-20

by

24/7 construction allows light rail tracks to be installed across Holgate Blvd 

The intersection of SE Holgate Blvd and 17th Avenue will be constrained for five days starting Sept. 12 while crews construct the light rail track crossing. Beginning at 7 a.m. Thursday, Sept. 12 through 6 p.m. on Friday, Sept. 20, Holgate will be narrowed to one lane in each direction, and 17th Avenue will be narrowed to one lane only with flaggers directing two-way traffic. Right turns may be prohibited for large vehicles.

The construction period is being extended by four days in order to take advantage of weather and further project progress. To minimize traffic impacts, construction will occur 24/7. Activities outside normal construction hours are approved under a noise variance from the City of Portland Noise Control Office, 503-823-7350.

For more information and updates, visit trimet.org/pm/construction

About the Portland-Milwaukie Light Rail Transit Project
The 7.3-mile project is the region’s sixth MAX construction project to be built and extends from the terminus of the MAX Green and Yellow lines at Portland State University in Downtown Portland to South Waterfront, SE Portland, Milwaukie and North Clackamas County. About the project: 

  • 7.3 miles
  • 10 stations
  • The first of its kind multi-modal bridge over the Willamette River that will carry light rail, buses, bikes, pedestrians and a future Portland Streetcar extension, but no private vehicles.
  • Opens Saturday, Sept. 12, 2015
  • Expands the MAX system to 60 miles and 97 stations  

Project partners 
The Federal Transit Administration, State of Oregon, Clackamas County, Metro, City of Milwaukie, Multnomah County, City of Oregon City, Oregon Department of Transportation, City of Portland, Portland Development Commission and TriMet.